Projects
Rasco had successfully implemented the following projects in Caspian region
Project | Client | Asset | Year |
---|---|---|---|
Combined Direct Current Voltage Gradient and Close interval Potential Survey of CP systems, for 900km of major transmission pipelines, including stations and inline facilities.. |
BP AzSPU | BTC/SCP Pipelines Azerbaijan | 2009 - 2010 |
Combined Direct Current Voltage Gradient and Close interval Potential Survey of CP systems, for 500km of major transmission pipelines, including stations and inline facilities.. |
BP AzSPU | BTC/SCP Pipelines Georgia | 2009 - 2010 |
Routine monitoring, maintenance and audit of Impressed Current CP systems, for 900km of major transmission pipelines, including stations and inline facilities. |
BP AzSPU | BTC/SCP Pipelines Azerbaijan | 2009 |
Routine monitoring, maintenance and audit of Impressed Current CP systems, 500km for major transmission pipelines, including stations and inline facilities. |
BP AzSPU | BTC/SCP Pipelines Georgia | 2009 |
Routine monitoring, maintenance and audit of Impressed Current CP systems, for 450km of major transmission pipeline, including stations and inline facilities. |
BP AzSPU | WREP Pipelines Azerbaijan | Since 2006 |
Routine monitoring, maintenance and audit of Impressed Current CP systems, for 250km of major transmission pipeline, including stations and inline facilities. |
BP AzSPU | WREP Pipelines Azerbaijan | Since 2006 |
Routine monitoring, maintenance and audit of Impressed Current CP systems for major oil and gas terminal. |
BP AzSPU | Sangachal Terminal Facility; Azerbaijan | Since 2006 |
Design, Supply, Install and commissioning of sacrificial anode CP system for BP Diesel Tank Farm and quayside buried import/ export lines |
BP AzSPU | BP Diesel Tank Farm; Azerbaijan | 2009 |
Design, Install and commissioning of CP integrated impressed current CP system for Sangachal Onshore Terminal |
BP AzSPU | Sangachal Terminal Facility; Azerbaijan | 2009 - 2010 |
Design, Supply, Install and commissioning of sacrificial anode CP system for 8" NICO pipeline between Sangachal Garadag Terminal operated by Corsscaspian and Sangachal Terminal |
Crosscaspian | Sangachal Garadag Terminal; Azerbaijan | 2009 - 2010 |
Design, Supply, Install and commissioning of sacrificial anode CP system for 8" NICO pipeline between Sangachal Garadag Terminal operated by Corsscaspian and Sangachal Terminal |
Encotec | Sangachal Terminal Facility; Azerbaijan | 2009 |
Design, install and commisioining of CP integrated impressed current CP system for Sangachal Onshore terminal |
BP | Sangachal Terminal Facility; Azerbaijan | 2009-2011 |
Monitoring, testing, maintenance and survey services for onshore and offshore pipelines, pipeline intermediate facilities, onshore terminals, stations and offshore jackets. The onshore pipeleines included BTC,SCP, WREP pipelines in Azerbaijan and Georgia. |
BP | BTC / SCP Pipeleines Azerbaijan, Georgia. WREP Pipeleine Azerbaijan, Georgia, Sangachal Terminal Facility, | 2009-2012 |
The above Onshore Pipeline and Facilities comprise of: • Sangachal Terminal • BTC Oil export Pipeline and facilities • SCP Gas Export Pipeline and facilities • WREP – Western Route Export Pipeline and facilities including SUPSA and the Onshore / Offshore Export Pipeline |
BP | BTC / SCP Pipeleines Azerbaijan, Georgia. WREP Pipeleine Azerbaijan, Georgia, Sangachal Terminal Facility, | 2009-2012 |
Design of CP system for Sangachal Garadagh Terminal |
SQT | SQT Oil Terminal ; Azerbaijan | 2013 |
Material supply and installation of CP system for Sangachal Garadagh Terminal storage tanks |
SQT | SQT Oil Terminal ; Azerbaijan | 2014 |
Material supply and installation of CP system for Ships |
Techmarine | Azerbaijan | 2015-present |
Gallery